Press Released

 

 
Dated: 12-10-2010  
  • PP10 Riyadh

BSI complete all the fabrication works related to PP10 Riyadh which contain the fabrication of the exhaust stack 36 units, turbine building , various steel structure buildings and 10Tanks with different size various from 27m to 5.5m in main time . The installation process with our crews at site is under process for the above scope and we achieve a very high progress reached to 85%


Dated: 12-10-2010  
  • Co-ordination with Saudi Oger in most of their projects

BSI shows more co-ordination with Saudi Oger in most of their projects and accomplished  the following works

  • Roof steel structure for A1 building for King Abdallah Int`l Convention Center Project [Fabrication, installation completed and under final hand over to consultant]
  • Princess Nora
                    - Dome for the administrative area at central library [ installation in process ]
                    - Steel roofing for the four units at grand lecture hall [fabrication in process]
  • KAFD Hotel (King Abdallah Financial District) [under design and shop drawing preparation]

Dated: 12-10-2010  
  • King Saud University

Finally and after one year of design variation from client the fabrication and installation process  had started and BSI is doing the best to cover the delay caused by others

 
 
ISO 9001:2000 ASME